Council is seeking comment on a priority list detailing the order in which Town and Village Plans for commercial centres will be prepared. The Town and Village Plans are important as they will aid in shaping the future character of Wollongong’s suburbs.
The draft priority list gives preference to the development of plans for major commercial centres such as Warrawong, Figtree and Unanderra. Also, work on some unfinished plans, such as the Draft Port Kembla Mainstreet Study, will recommence in the near future.
The draft priority list is as follows:
| |
Project |
Proposed commencement |
Anticipated completion |
| 1 |
Warrawong Regional Centre review |
March 2010 |
December 2010 |
| 2 |
Draft Port Kembla Mainstreet Study |
Recommence in March 2010 |
June 2010 |
| 3 |
Review of Figtree and Unanderra Major Towns |
April 2010 |
December 2010 |
| 4 |
Review of Fairy Meadow Major Town |
Recommence in September 2010 |
June 2011 |
| 5 |
Helensburgh Town Plan |
September 2010 |
March 2011 |
| 6 |
Berkeley Town Centre Study |
Recommence in February 2011 |
August 2011 |
| 7 |
Mt Kembla Site Specific DCP review |
February 2011 |
August 2011 |
| 8 |
Gwynneville Precinct Plan |
March 2011 |
September 2011 |
| 9 |
Bulli Town Centre Plan |
July 2011 |
December 2011 |
| 10 |
Windang Town Centre Plan |
July 2011 |
December 2011 |
Any comments should be submitted to Council by 18 March 2010. A copy of the report considered by Council on 2 February 2010 is located on the right..